All estimates should be over estimates. There is no set order here. See the PySmartRoadmap for less detail and more order.

Extraction

  • Add Optimal Extraction (1/2 day) - initial implementation done, fine tuning needed
  • Fine tune source highlighting (1 hour - subject to user feedback)
  • Proper history notes (1/2 day)
  • Partial collapse (1 day)
  • Update Dynamic RSRF (1/2 day)
  • Add settings system (bitmask and others) (1 day)
  • Fix flux calibration (0-2 days 3 days)
  • Increase polyclip speed (1/2 day 1/2 day)
  • Add Gaussian Extraction (1 day) - partially completed but currently on hold

Sky Subraction

  • Implement (2 days)

View Image

  • Fine tune brightness/contrast (1 hr - subject to user feedback)
  • Add WCS display/coordinate display (1/2 day)
  • Remove toolbox GUI widget (1/2 day 1/2 hour)
  • Add wavelength display (1/2 day 1 hour)
  • Add save to ps/jpeg/gif (1 hr)

Header

  • Insert/Remove Line (1/2 day)
  • Fix multiple file GUI (1/2 day)

Notes

  • Add bold/italic support. (1/2 day) Delayed unless there are user requests
  • Add ability to insert references to other records. (1/2 day) Delayed unless there are user requests

ImOps

  • Fair Coadd and Weighted Mean (1/2 day 1 hour)

Cleaning

  • Custom Rogue Mask Creation (1 day)
  • Automatic Rogue Mask Creation (1 day)
  • Wavelet Decomposition Cleaning Algorithm (1 day)

Record Management

  • Implement saving system (1 day)
  • Recognize deleted/modified tags (2 hours 1/2 hour)
  • Implement Proper record deletion and hiding (1 day 1 day)
  • Implement Proper tag/branch deletion (1 day)

Calibration Files

  • Add settings GUI (1/2 day)
  • Implement Calibration file system (2 days 2 days)

Spectrum Viewer

  • Add line fitter (2 days)
  • Add black body fitter (3 days)
  • Put functions back in
  • Make GUI simpler and remove toolbox GUI widget (1 day 1/2 day)
  • Add more powerful functions system (1 day 2 hours)
  • Speed up section processing (1/2 day 1/2 day)

SpecOps

  • Create GUI (1/2 day 2 hours)
  • Create Group Operations (1/2 day)

-- DavidLevitan - 16 Apr 2007

 